It's a new week and that brings with it a whole new set of construction activities. Drainage pipes are arriving, water lines west and south of the building are being tapped into for the new sources of water supply and more holes are being dug for exploration.
There will be a new storm sewer line installed from where the 'B' squad softball field was, which now will become a retetion pond, which will extend to the west property line taking a path through the Varsity softball field and continue through the old tennis courts and then go south to Minnesota Street. Fraser Construction has run into some rock and they need to do some blasting to break it up. Our neighbors have been notified by The Loss Protection Associates and their property has been video taped. BLASTING OF ROCK WILL SOMETIMES TAKE PLACE TUESDAY through FRIDAY THIS WEEK BETWEEN 8 a.m. and 4 p.m. NO ONE WILL BE ALLOWED IN ANY OUTSIDE AREAS OF THE HIGH SCHOOL BUILDING DURING THE BLASTING. People will be out in the areas when this occurs to advise anyone to clear the area.
I hope to post another update Tuesday and will advise more on some of the projects that are taking place.